Constructions Progress - July 2025

   

Nov 2024

Construction started

25% complete

Overall progress

R59.6 million

Current spend

March 2026

Expected completion

Construction Updates by Area

Training & Lecture Facilities

95% complete
  • Fully operational lecture rooms
  • Mechanical ventilation and electrical installations finalised
  • Only AV installation outstanding

Sports & Health Building

19% under construction
  • First-floor slab casting substantially advanced
  • Roofing underway
  • Ground-floor service installations in progress
  • Rooftop conference venue plans underway

Aquatics Centre

Therapeutic Aquatics Centre 10%
  • Ground-floor pools completed, waterproofed and backfilled
  • Upper-level slab preparation underway
  • Roof construction scheduled to begin soon
Main Pool Area 32%
  • Ground-floor works completed
  • Ring beams and box gutter works in progress
  • Roof structure installation next

Upcoming Developments

Rooftop Conference & Event Venue

A new conference and entertainment venue is planned on the roof of the Sports & Health Building, offering panoramic views and a premium space for events, conferences, and gatherings.

High-Performance Athlete Accommodation

Dedicated accommodation is being developed for visiting professional athletes and teams, located within walking distance of the complex and designed to support elite performance.